One of the three documents required with every claim (cl. 26.2(b)(v)) — with the
program status report (the weekly report) and the Financial Statement. Saves in your browser.
PAYMENT REGISTER
Bitterns Recycling Field Piping Installation · clause 26.2(b)(v)
From
DTL (WA) Pty Ltd2/28 Horus Bend, Bibra Lake WA 6163
ABN: 45 677 646 454
To
Shark Bay Resources Pty LtdABN: 88 079 088 636
Attn: Mr John Stephens
References
PO-
182113 · SBS10627
Job DTL-PRJ0072
Terms: 30 D F-I-M-E
Claims under the contract — claimed · certified · invoiced · paid · all figures exclude GST
| Claim |
Claim date |
Claimed |
Cert. date |
Certified |
Variance |
Tax invoice |
Invoiced |
Paid date |
Paid |
Outstanding |
Variance = certified less claimed. Where a certificate is for less than claimed,
clause 26.3(b)(ii) requires the Principal Representative to state why — record the reason against the claim.
Outstanding = invoiced less paid.
Approved variations — approved by the Principal to date
| VO no. | Description |
Approved | Amount |
Only variations approved by the Principal belong here. Variation work executed must also be
shown separately in the claim itself (cl. 26.2(b)(ii)).
Not printed — for DTL only. SBR's Schedule 8 pack has no template for the payment register or the
financial statement, so these are ours. Sent to the Principal Representative for approval; if SBR issues
templates, we adopt theirs.